September 3, 2005

3127 N Ashland Envelope Complete

July 22, 2005

Siding Starts @ 3127 N Ashland


July 8, 2005

Masonry 99% complete @ 3127 N Ashland


May 11, 2005

Steel Set @ 3127 N Ashland


May 4, 2005

Framing Starts @ 3127 N Ashland


April 8, 2005

Masonry Progress @ 3127 N Ashland


March 27, 2005

Masonry Starts @ 3127 N Ashland


March 22, 2005

Moment Frame @ 3127 N Ashland


February 8, 2005

Foundation Construction @ 3127 N Ashland


February 4, 2005

Footings complete @ 3127 N Ashland Ave


February 1, 2005

Work Begins @ 3127 N Ashland