October 18, 2007

Tile + Counter Install Begins - Chang Residence

58.jpg59.jpg24.jpg41.jpg70.jpg71.jpg


September 21, 2007

Driveway + Walkways - Chang Residence

77.jpg79.jpg83.jpg80.jpg81.jpg82.jpg


September 10, 2007

Cabinets Installed - Chang Residence

74.jpg63.jpg64.jpg66.jpg67.jpg69.jpg


August 15, 2007

Wood Ceiling Install - Chang Residence

22.jpg42.jpg54.jpg55.jpg56.jpg57.jpg


July 9, 2007

Drywall + Fry-reglet install begins - Chang Residence

48.jpg45.jpg17.jpg16.jpg52.jpg51.jpg


May 7, 2007

Travertine Stone Veneer Install - Chang Residence

20.jpg21.jpg18.jpg26.jpg37.jpg13.jpg

February 7, 2007

Insulation + Resilient Channel Install Begins - Chang Residence

44.jpg11.jpg12.jpg

January 7, 2007

Building wrap + stucco - Chang Residence

32.jpg31.jpg10.jpg35.jpg36.jpg15.jpg

October 7, 2006

Window install continues - Chang Residence

2.jpg3.jpg4.jpg5.jpg6.jpg73.jpg


August 24, 2006

Windows finally arrive + install begins - Chang Residence

August 14, 2006

Steel stairs installed - Chang Residence

July 31, 2006

Steel canopies, sunshades + balcony structures installed - Chang Residence



May 31, 2006

Mechanical, electric + plumbing systems installed - Chang Residence

March 14, 2006

Guest house framing begins - Chang Residence


January 18, 2006

Second floor framing begins - Chang Residence


December 25, 2005

First floor framing begins - Chang Residence


November 4, 2005

Pool install begins - Chang Residence


October 10, 2005

Masonry work begins - Chang Residence

May 29, 2005

Waterproofing + Basement framing + First floor slab - Chang Residence

February 7, 2005

Excavation and foundation work begins - Chang Residence